White Flint is exploding with construction. Following is a list of updates regarding schedules and strategies.

Chapman Extended
Utility relocations to be completed by Summer 2014, and construction will start in Summer 2014 and will end in Summer 2015.

White Flint District East: Transportation
Design of all road projects began in FY12 and is expected to conclude in FY16. Construction of Executive Boulevard Extended East from Rockville Pike/MD 355 to a New Private Street will begin in FY17 and is expected to conclude in FY18, subject to tax district affordability. Design of Executive Boulevard East Extended was delayed due to coordination between the stakeholders over the road alignment. Design for the bridge across the the WMATA tracks adjacent to the White Flint Metro Station has been delayed due to negotiations between WMATA, State Highway Administration (SHA), the County, and the developers; bridge design will begin after a Memorandum of Understanding between the parties has been finalized.

White Flint District West: Transportation*
Design is underway on all road projects in the western workaround, with the exception of the Rockville Pike segment, and will conclude in FY15 (FY15 design is funded through White Flint West Workaround). Design of the Rockville Pike section will begin in FY19 and will conclude in FY21 in order to coordinate with the implementation of the Rapid Transit System (RTS) (CIP #501318). Some property acquisition may occur on this section in FY20. The current expenditure/funding schedule assumes that land needed for road construction will be dedicated by the major developers in a timely manner.

Montrose Parkway East
The design and land acquisition phase is expected to be complete in mid-FY16. Construction is expected to start in FY19 and will be completed in approximately 3.5 years.

Kennedy Shriver Aquatic Center Building Envelope Improvement
Design to start in FY18, and construction to start in FY19